Heathrow bosses ‘warned about substation’ days before major power outage, MP committee hears
Heathrow Airport bosses had been warned of a potential substation failures less than a week before a major power outage closed the airport for a day, a committee of MPs has heard.
The chief executive of Heathrow Airline Operators’ Committee Nigel Wicking told MPs of the Transport Committee he raised issues about resilience on 15 March after cable and wiring took out lights on a runway.
A fire at an electricity substation in west London meant the power supply was disrupted to Europe’s largest airport for a day – causing travel chaos for around 200,000 passengers.
“I’d actually warned Heathrow of concerns that we had with regard to the substations and my concern was resilience”, Mr Wicking said.
“So the first occasion was to team Heathrow director on the 15th of the month of March. And then I also spoke to the chief operating officer and chief customer officer two days before regarding this concern.
“And it was following a number of, a couple of incidents of, unfortunately, theft, of wire and cable around some of the power supply that on one of those occasions, took out the lights on the runway for a period of time. That obviously made me concerned.”
Mr Wicking also said he believed Heathrow’s Terminal 5 could have been ready to receive repatriation flights by “late morning” on the day of the closure, and that “there was opportunity also to get flights out”.
However, Heathrow chief executive Thomas Woldbye said keeping the airport open during last month’s power outage would have been “disastrous”.
This breaking news story is being updated and more details will be published shortly.
Please refresh the page for the fullest version.
You can receive breaking news alerts on a smartphone or tablet via the Sky News app. You can also follow us on WhatsApp and subscribe to our YouTube channel to keep up with the latest news.